GC pay-app rules
Turner Construction
Turner Construction requires Form CW-PP-2024 lien waivers (not AIA G706), strict SOV-to-G702 reconciliation, and officer-signed waivers. Here's the full pay-app rule set.
Pay-App Requirements for Turner Construction Subcontractors
Turner Construction is the largest commercial GC in the United States by revenue. They run pay-app intake through Procore (primary) plus internal tools depending on the region. Their sub billing team is automated enough that packets failing pre-flight checks bounce within hours of submission, and manual enough that a human-readable exception note can resolve a soft reject if you catch it early.
If you bill Turner monthly on AIA G702/G703, this page covers what their billing team requires, what bounces their packets, and the common reasons subs lose 30–60 days of cash on Turner work.
Portal & submission
- Primary portal: Procore (Turner is one of the largest Procore
customers and uses it for pay-app intake on most jobs).
- Regional variation: some Turner regions still use internal
tools or a Turner-customized Procore configuration; check your subcontract's payment-application addendum.
- Cutoff: typically the 25th of the month. Miss it and you
wait a full cycle.
- Pay cycle: 30 days from a clean submission, contractually.
Realistic expectation is 35–45 days from the cutoff.
Lien waiver form
This is the single most common Turner-specific rejection cause.
Turner requires their Conditional Waiver and Release (Form CW-PP-2024) for every progress payment. The standard AIA G706 will auto-bounce in their portal. Most subs new to Turner submit the AIA G706 and wait 24–48 hours before learning the packet failed pre-flight.
Form set you should keep on file per Turner job:
- CW-PP-2024 — Conditional Waiver on Progress Payment (every
cycle).
- UCW-PP-2024 — Unconditional Waiver on Progress Payment (only
after the prior period's check has cleared).
- CW-FP-2024 — Conditional Waiver on Final Payment.
- UCW-FP-2024 — Unconditional Waiver on Final Payment (only
after the final check has cleared).
Authorized signer: Turner requires waivers signed by a corporate officer on file with Turner's risk team. Estimator and PM signatures get rejected. Most subs we audit don't keep an authorized-signer roster per GC, so the estimator-signed waiver pattern is endemic.
Lower-tier waivers: Turner requires waivers from any vendor billed >$500 in the period. This includes equipment rentals, material suppliers, and 2nd-tier subs. Missing lower-tier waivers are the #4 rejection cause on Turner packets.
SOV and change-order reconciliation
Turner's intake validates the G703 column F sum against the G702 contract sum (line 1 + executed COs). The validation tolerance is tight — within rounding. Common failure pattern:
- Change order #N is executed, signed, and billed.
- The CO amount is added to the G702 (line 3 — change orders to
date) but the corresponding new line items are not added to the G703 continuation sheet.
- G703 column F now sums $X below the G702 contract sum.
- Packet auto-bounces.
Fix: before submission, reconcile your G703 against the live change-order log every cycle. Add a row to the G703 for every executed CO, even if the dollar value is zero (allowance reserves, no-cost time extensions).
Stored materials
Turner requires the following for any G703 line billing stored materials:
- Vendor invoice for the stored material.
- Photographs of the stored materials at the off-site location
(most subs include 4 photos: front and back of the pallet, label close-up showing serial numbers, and a wide shot showing the storage location).
- An off-site stored-materials insurance rider naming Turner as
additional insured.
- Bill of sale transferring title to Turner per the subcontract.
These are reproduced in Exhibit D of most Turner subcontracts.
Certified payroll (public works)
On federal projects, Turner requires WH-347 weekly. On state projects, the equivalent state form (e.g., California's DIR eCPR). Missing CPR uploads block your next pay app at the awarding-body level, not at Turner — but the practical effect is the same: no billing until the CPR is current.
If you're working a Turner federal project under Davis-Bacon, the WH-347 must be uploaded to Turner's documentation portal each week. Turner's PMs will typically not chase you for it; they'll simply withhold the next pay app until it's complete.
Top rejection causes on Turner packets
In SubCash's rejection taxonomy:
- R024 — Turner project uses AIA G706 instead of required Exhibit F (top): AIA G706 in place of
CW-PP-2024.
- R001 — SOV sum mismatch after change order.
- R010 — Waiver signed by party without binding authority (estimator
instead of officer).
- R017 — Stored materials missing photos (GC-specific) (missing
photos, COI rider, or bill of sale).
- R021 — Certificate of Insurance expired before or during pay period mid-cycle.
Free Turner Pay-App Checker
Paste your Turner-bound packet text or drop a PDF. The free checker scans for the 5 rejection causes above plus the rest of SubCash's rule library, returns rule-cited findings in 30 seconds, and runs entirely in your browser — no upload to a server.
Get a $99 Cash-at-Risk Audit on your Turner packets
Send us one billing cycle of your Turner packets and your last 90 days of rejection emails. We return a fixed-format report showing exactly which dollars are at risk, why, and what to fix this week.
5 business days. Refund if we don't find at least $10K of cash at risk or 5+ hours/month of recoverable admin time.
FAQ
Q: Does Turner accept AIA G706 lien waivers? A: No. Turner requires their custom Form CW-PP-2024 for every progress payment. AIA G706 submissions auto-bounce in their portal.
Q: What is Turner's pay-app cutoff? A: Typically the 25th of the month, with payment due 30 days from a clean submission. Realistic time-to-cash is 35–45 days from cutoff once portal review and approval cycles are factored in.
Q: What's Turner's retainage schedule? A: 10% withheld until 50% complete, then 5% withheld through substantial completion. Released per the subcontract — typically 30–60 days post substantial-completion certificate.
Q: Can I sign a Turner waiver as a project manager? A: Probably not. Turner's risk team requires waivers signed by a corporate officer on file with Turner. PM and estimator signatures typically get rejected. Maintain an authorized-signer roster per GC and route your e-sign requests to the right person.
Q: How does SubCash help with Turner-specific packet prep? A: SubCash detects when a packet is bound for Turner and applies their rule overlay automatically: enforces CW-PP-2024 form usage, reconciles G702 against G703 against the executed CO log, routes e-sign to your authorized officer, validates stored-materials documentation, and tracks COI expiration ahead of Turner's verification window. The free Pay-App Checker shows the rule hits; the $499/mo SubCash OS subscription prevents them every cycle on every active job.